Project Overview
The Route 24 and Columbia Turnpike (CR 510) Interchange Improvements Concept Development project examined four alternatives to improve traffic movement between the Route 24 eastbound off-ramp and the intersection of Columbia Turnpike (CR 510) and Park Avenue (CR 623), and to reduce congestion at this intersection.
The municipalities in the area of the Route 24 and Columbia Turnpike interchange have had significant commercial and residential growth over the past decades. The interchange, located at the border of Morris and Hanover Townships and Florham Park Borough, is heavily used by commuters, and the nearby intersection of Columbia Turnpike and Park Avenue is highly congested.
Columbia Turnpike is further affected in the morning by the weaving movement of traffic exiting Route 24 eastbound onto Columbia Turnpike westbound and turning left onto Park Avenue southbound; this movement creates congestion that backs up onto Route 24 in the morning.
Route 24 is under NJDOT’s jurisdiction, and Columbia Turnpike and Park Avenue are under Morris County’s jurisdiction.
NJDOT hired IH Engineers, PC to conduct the CD study. The initial phase of Local Project Delivery Process is the Local Concept Development (LCD) phase in which sponsors, local officials, and the public identify and compare reasonable alternatives and strategies that address the purpose and need statement and select a preliminary preferred alternative (PPA). NJDOT and the consultant team held two Public Officials meetings and conducted a Public Information Center as they advanced this study. The Report was completed in January 2021.
In 2025, Morris County retained Greenman-Pedersen, Inc. (GPI) to advance the PPA to the next phase, Local Preliminary Engineering (LPE) to develop the Approved Project Plan (APP).
Timeline
01
Data Collection
Continuous
02
Community Outreach/Input
Duration of Study with Initial Public Information Center - Spring 2027
03
Design Exception Approval
Summer 2027
04
Approved Project Plan (APP)
Public Information Center - Fall 2027
05
Approved Environmental Document (Anticipated Environmental Assessment)
Winter 2027
06
Final Preliminary Engineering Report
Winter 2027